Azerbaijan Wind IPP

Azerbaijan Wind IPP

The Khizi-Absheron 240 MW Wind Farm is a greenfield Independent Power Project (IPP) developed by ACWA Power in the Republic of Azerbaijan. It is the first large-scale, independently developed wind energy project in the country and plays a key role in Azerbaijan’s renewable energy transition.

The wind power plant, with an installed capacity of 240 MW, is located across the Absheron (Area 1) and Khizi (Khizi 3) districts, specifically in the Chayli and Sitalchay villages. It will consist of 37 wind turbines, 12 in Absheron and 25 in Khizi.

The first wind turbine was installed on November 23, 2024. All 12 turbines at the Absheron site have been successfully installed and are scheduled to begin operation in Q3 2025. Installation has also commenced at the Khizi site, with the entire project expected to be fully operational by Q4 2025.

Once completed, the wind farm will generate up to 907 GWh of clean electricity annually, enough to power more than 300,000 Azerbaijani households. In addition to supporting energy diversification and national sustainability goals, the project will help reduce carbon dioxide emissions by approximately 400,000 tons per year.

Key documents

  • Area 1 ESIA Volume 1 Non-Technical Summary

  • Area 1 ESIA Volume II Main Report

  • Area 1 ESIA Volume III Environmental & Social Monitoring

  • Area 1 ESIA Volume IV Appendices

  • Area 1 ESIA Consultation Disclosure

  • Area 1 ESIA Addendum

  • Area 1 Stakeholder Engagement Plan

  • Area 1 Livelihood Restoration Plan

  • Area 1 Environmental & Social Management Plan

  • Khizi 3 ESIA Volume I Non-Technical Summary

  • Khizi 3 ESIA Volume II Main Report

  • Khizi 3 ESIA Volume III Environmental & Social Monitoring

  • Khizi 3 ESIA Volume IV Appendices

  • Khizi 3 ESIA Consultation Disclosure Report

  • Khizi 3 ESIA Addendum

  • Khizi 3 Stakeholder Engagement Plan

  • Khizi 3 Livelihood Restoration Plan

  • Khizi 3 Environmental & Social Management Plan

  • Area 1 ESIA Volume I Non-Technical Summary

  • Area 1 ESIA Volume II Main Report

  • Area 1 ESIA Volume III Environmental & Social Monitoring

  • Area 1 ESIA Volume IV Appendices

  • Area 1 Stakeholder Engagement Plan

  • Area 1 Livelihood Restoration Plan

  • Area 1 Environmental & Social Management Plan

  • Khizi 3 ESIA Volume I Non-Technical Summary

  • Khizi 3 ESIA Volume II Main Report

  • Khizi 3 ESIA Volume III Environmental & Social Monitoring

  • Khizi 3 ESIA Volume IV Appendices

  • Khizi 3 Stakeholder Engagement Plan

  • Khizi 3 Livelihood Restoration Plan

  • Khizi 3 Environmental & Social Management Plan

Key facts

  • Location

    45 KM North-West of Baku; Khizi and Absheron regions, Azerbaijan

  • Offtaker

    "Azerenerji" OJSC

  • Capacity

    240 MW

  • Technology

    Envision, 6.5MW WTG (EN171/6.5)

  • Investment cost

    US$ 337.9 million

  • Commercial operations date

    Absheron: Q3 2025 Khizi: Q4 2025

  • Acwa share

    100%

  • Offtake contract

    25 Years PPA; BOO basis

  • Other investors

    EBRD (syndicated with OFID, ILX and PGGM )

  • Project company

    ACWA Power Azerbaijan Renewable Energy LLC

  • Operations & maintenance company

    Acwa Operations

  • Engineering, procurement & construction company

    Hua Dong Engineering Corporation (HDEC)